300 Burdett Road tasks to completion

Remaining tasks to complete on 300 Burdett Road new extension

To-dos

Stage payment 1
  • Electrical 1st fit Sat, 16 Apr 2011
  • Plumbing 1st fit Sat, 16 Apr 2011
  • Install ceiling Fri, 15 Apr 2011
  • Plastering (rendering/browning) Sat, 16 Apr 2011
Stage payment 2
  • Plastering (skimming)
  • Guttering
  • Slate laying & sealing
  • Woodwork stain & varnish
Final stage payment
  • Gas Safe certificate for boiler and hob installation
  • Sink waste mechanism
  • Tap hot & cold swap
  • Make thermostat work
  • Tap in lightwell
  • Slate polishing
  • Front door painted
  • Rubbish & unused materials taken away
  • Neighbour's wall pointed
  • Neighbour's trellis fixed (restored as it was prior to job)
  • All snagging finished (tasks will be added to this list)
  • Raise worktop to 850mm
  • Box out cables under pillar
  • Screw in oven
  • Finish around door and window frames
  • Bricks under new window - match mortar colour and gap
  • Electrical 2nd fit (lightwell)
  • Plumbing 2nd fit (sink & tap)
  • Lightwell 1st fit
  • Rocking tile (and slightly rocky one next to it)
  • Tumble dryer venting
  • Final site clearance
  • Slate grouting
  • Skirting
  • Architraves
  • External power socket
  • Smell from drains in kitchen
  • Skirting board in hall
  • Old 30A cable in hall
  • Scratched doors
  • Door handles Fri, 20 May 2011
  • Grout stains on kickplate